Installation Guide:
Post Frame Applications
Purlins or Flush Frame Application Walls
Product
 
R-Value
Horizontal Heat Flow: R-6.7*
* System R-Value is for two enclosed air spaces. Additional R-1.7 added for a still air film.
Note: If interior finish is not installed, then only one enclosed airspace would apply.
 
Instructions
  1. Wrap the Flexfoil around the inside of the framework.
  2. Fasten the Flexfoil to the outside of each girt.
  3. Leave enough Flexfoil between the girts to allow the material to bow inward, creating a 3/4" enclosed airspace.
  4. If Flexfoil is to be used as a vapour barrier, all seams must be taped using Flexfoil reflective tape.
  5. The interior finishes to be installed using approved attachment methods.